So much for being able to move in by the end of this month. It'll be Christmas if I'm lucky.
The floorboards will be delivered tomorrow or the next day and then they will start to install the boards on Tuesday next week. Then it's a three or four week process. That takes us to 13 December. Then the carpet will have to be installed. Luckily, that only takes one day. Let's say 15 December. Then the builder has to do his finishing off things, eg install the skirting boards downstairs, put in the oven, dishwasher etc. That would be all well and good, except the building trades take a month off from mid-December to mid-January.......
Maybe I'm just being a pessimist.